Most house demolitions take one to three days of machine time and most garages take under a day — but the lead time before that, not the teardown, is what sets your date. Permits, the IEPA asbestos notification where it applies, and utility disconnects run days to weeks and have to be finished before a machine moves. Brohez Trucking LLC runs both clocks for you on demolition work across central Illinois, inside 60 miles of Mattoon. Call or text a photo to (217) 809-0779 and you get a straight answer on timing the same day.
One to three days on most houses, under a day on most garages — that is the machine time: teardown, haul, backfill and final grade. But two clocks run on every demolition, and the other one is longer. Lead time — permits, the IEPA asbestos notice where it applies, and the utility disconnect — runs days to weeks and is what actually sets your start date. The disconnect has to be requested by you as the account holder and is the most common reason a date slips, so make that call first. We give you a timeline with the quote: (217) 809-0779.
"How long does it take to demolish a house?" is the second question almost everybody asks, right after what it costs — and it's the one that gets answered worst, because most answers only count the part with the machine in it.
Here's the honest version: the machine work is usually the shortest phase of a demolition. On a typical central Illinois teardown, the actual tearing down is a day or two. The timeline — from the day you decide to the day the ground is clean and seeded — is mostly made of things that happen before we ever show up.
The Two Clocks: Lead Time And Machine Time
Every demolition runs on two separate clocks, and confusing them is why people get surprised.
- Lead time — permits, notifications, and utility disconnects. Days to weeks. Almost none of it is in anyone's control once it's started, which is why it gets started first.
- Machine time — the teardown, the loading, the hauling, the backfill and the final grade. Hours to days, and it's the part you can actually watch.
When somebody tells you a house comes down in a day, they're quoting machine time. Both numbers are real; you just need them separately to plan anything.
The Five Phases Of A Demolition, And How Long Each One Takes
Most of the timeline lives outside the machine. Here are the five phases in the order they actually happen on a central Illinois job, with the honest duration of each.
1. Planning and permitting — a few days to a few weeks
Estimate visit, scope agreed, then the demolition permit. Pulling the permit is our job, not yours. Some towns issue it the same week over the counter; others put it in front of a board that meets once a month, and that meeting date sets your start more than anything we do. Ask us early which one your address falls under — we already know for most of the towns inside our radius, and it is the cheapest week you will ever save.
If the permit is the part you are actually trying to time, we answer that on its own page rather than here: how long it takes to get a demolition permit in Illinois, town by town, including which authorities issue over the counter and which wait on a monthly board meeting. This page is about how long the demolition takes once that permit is in hand.
2. Utility disconnection — usually the longest wait, and not ours to shorten
You call the utility companies and have electric, gas, and water disconnected and removed at the meter before we start. That wording is deliberate: a closed valve or a pulled breaker is not a disconnect, and a job that shows up to a live meter stops on the spot. Utility crews schedule on their own calendar, not ours, and on a busy month that can run weeks — so make those calls the day you decide, before anything else on this list.
The private side is ours. We disconnect a private well or a propane tank if the property has one, and we cap the sewer. We also call in JULIE 8-1-1 locates before we dig — worth saying plainly, because locating a buried line and disconnecting a service are two different things and only one of them is on your list.
3. Asbestos and hazardous material — zero to about two weeks
This phase is either free or it is the long pole, and which one depends entirely on what kind of building it is. A single-family house being torn down for its owner carries a survey exemption in Illinois. A commercial, institutional, agricultural, or over-four-unit building does not — it needs a licensed survey and a written 10-working-day notification to Illinois EPA before work starts, and that ten-day clock cannot be compressed, shortened, or started retroactively. A barn is an agricultural structure rather than a residence, so it gets no exemption whatever its age. We coordinate the survey and the notice and build the clock into the schedule.
4. Structural teardown — a day or two
The part everybody pictures, and the shortest part of the job. On a typical central Illinois house the machine work is one to two days. A large commercial building, a concrete structure, or a tight site with hand-work around a neighbouring wall runs longer, but the teardown is rarely what makes a demolition slow.
5. Debris removal and site restoration — a day to several
Debris out to a permitted disposal site, metal pulled for scrap, then the part most quotes go quiet about: the foundation, footings, and slab if they are coming out, the hole backfilled in compacted lifts so the ground does not sink in two years, and the site graded and seeded. Backfilling a basement by pushing the walls in and dumping loose dirt on top is faster and it is the reason so many old teardown sites have a dish in them.
Read those five against the two clocks above and the shape is obvious: phases 1, 2 and 3 are lead time and they are where your weeks go; phases 4 and 5 are machine time and they are measured in days. The single fastest thing you can do to shorten a demolition is make the utility calls today.
Lead Time — What Actually Sets Your Start Date
The utility disconnect (usually the long pole)
Electric, gas and water have to be disconnected and removed at the meter by the utility companies, and they'll only take that request from the account holder — you. A closed valve isn't a disconnect, and a job genuinely cannot start without it. On a residential drop this can be quick; on a commercial service or a gas main it can run weeks. This is the call to make on day one, before you've even settled on a contractor.
The paperwork ahead of the machines
Inside a city or village the paperwork has to clear before anything comes down, and out on unincorporated county ground an agricultural building often needs nothing local at all — which is why farm jobs move faster. How long that takes, and what each authority wants, is its own subject and it is written up in full on do you need a permit to demolish a building in Illinois.
The asbestos notification — only on some buildings
This is the piece that catches people, and it cuts the opposite way from what most expect. A single-family private residence is exempt: no survey, no notice. A commercial, institutional, ag or over-four-unit building is not — it needs a licensed survey and a written 10-working-day notification to Illinois EPA before work starts. Ten working days is two calendar weeks, and nothing compresses it. If abatement is required on top of that, a licensed contractor has to remove the material before we demolish, and that's more calendar again.
The full breakdown is in do you need a permit to demolish a building in Illinois — including how long a demolition permit actually takes downstate, which is a different answer from the Chicago-area timelines most search results give you.
Scheduling and weather
Then there's the queue and the ground. We're honest about where you land in the schedule when we quote it. Wet ground is the other one: heavy machines and loaded tandems on saturated clay make a mess that somebody has to fix afterward, so after a long soaking rain the right call is often to wait a few days. That's covered in why we wait on saturated ground.
Machine Time — Roughly, By Structure
Once we're on site with everything cleared, here's what the active work usually looks like. These are typical, not promises — every one of them moves with size, access, haul distance, and what's under the building.
- Shed or small outbuilding — a few hours. Often part of a larger day.
- Detached garage — most come down and haul out inside a day. A big three-car with a slab coming out can run into a second.
- Mobile home — usually a day, sometimes less. The pad and blocking decide the tail end.
- House, slab-on-grade — a day to two. Structure down and hauled, then the slab.
- House with a full basement — two to three days is typical. The hole is the work: walls broken in, backfilled in lifts, compacted, graded.
- Barn or pole barn — a day to two for most, longer on a big timber-frame with a foundation and a concrete floor.
- Grain bin — a bin or two in a day is common; a cluster with a leg and augers is a multi-day farmstead job.
- Silo — a controlled sequence, usually a day or more depending on what it's built from and what's still in the tube.
- Commercial building — genuinely varies. Size, steel content, concrete underneath, and whether anything adjacent stays in use.
The pattern to notice: what's under the building drives the tail end more than the building drives the front end. Bringing a house down is fast. Breaking out a basement, backfilling it properly in lifts and leaving a graded, seedable lot is the part that takes real time — and it's the part that gets cut when somebody quotes an unrealistically short job.
What Makes A Demolition Take Longer
- Waiting on the utility disconnect. Number one, every year. Make the call early.
- An asbestos finding on a non-exempt building. Survey, notice, then abatement before we start.
- A basement or foundation nobody knew was there. Old farmsteads hide cisterns, cellars and footings.
- Tight access. If trucks can't get close, everything moves twice.
- Haul distance. The round trip to a disposal site is a real part of the day.
- Contents still in the building. Everything left inside gets loaded and hauled with the structure.
- Wet ground. Not lost time exactly — traded, so we're not repairing ruts later.
- Something attached that stays. Separating cleanly is careful work.
How To Make It Go Faster
Four things genuinely move your date up, and three of them are free:
- Call the utility companies the day you decide. Nothing else on this list matters as much.
- Clear the building out beforehand if you're going to. Everything left inside becomes material we load and haul.
- Decide the concrete question early — slab and foundation in or out. It changes the crew, the trucks and the day count.
- Tell us your real deadline. If a closing, a lease or a build sets it, say so on the first call. It changes what we start first.
So How Long Will Mine Take?
For most single-family teardowns in central Illinois: figure a week or two of lead time if the utility disconnect cooperates, then one to three days of active work, and a final grade at the end of it. For a commercial building, add the survey and the ten working days of notice to the front — that's usually the piece that sets the date.
We give you a timeline with the quote, not just a number, and we tell you which items on it are ours and which are waiting on somebody else. If a date is driving your project, say so at the walk-through and we'll build the sequence backwards from it.
"We hired Levy for a large demo job and dirt removal. They showed up on time, worked hard, and completed the job faster than I expected. What impressed me most was how clean they left the site afterwards — no mess left behind."
"Great Service and Great Price! They continued working for 3 days to demolish three buildings and removed all the debris to dumpsters that I ordered. Then, they also came in with dirt to fill the whole backyard. Strongly recommended!"
"Very responsive, fair pricing, and easy to work with. Did a great job for our project."
Every one of these is a real Google review from a real central Illinois customer — see them all on our reviews page.